MEUR 50Unit TENT A5 for revitalization project: Hitachi Power Europe, Alstom and Doosan leading the works

Major revitalization project on unit A5 on biggest power plant in Balkans will include boiler works, piping system, turbine and mills reconstruction. Reconstruction and works on several Lots will improve power plant efficiency and environmental protection.

Revitalization of the Unit TENT ?5 starts on 1 June and will last until 30 September 2012, it was said at the meeting of the main

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia targets 2027 construction start for €1.5 billion Čebren-Galište hydro project

North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects, reviving a combined investment of up to €1.5 billion after years of unsuccessful concession attempts. Čebren is planned with a capacity of around 333...

Greek court shuts solar permitting loophole after 185 MW project ruling

Greece’s highest administrative court has overturned approvals for a 185 MW solar development that had been divided into dozens of smaller projects, potentially tightening permitting requirements across the country’s utility-scale photovoltaic pipeline. The Council of State cancelled 186 preliminary producer...

Romania backs 1.3 GW Dama Solar project with €561 million financing

Romania has secured up to €561 million in financing for the 1.3 GWp Dama Solar project, clearing the way for construction of one of Europe’s largest onshore renewable-energy developments. Developer Rezolv Energy said the syndicated financing involves 14 lenders, with...
Supported byVirtu Energy