HomeSEE Energy NewsMacedonia: Restart of...

Macedonia: Restart of TPP Oslomej project

Macedonian state-owned power utility ELEM, in cooperation with the Ministry of Environment and Spatial Planning, has opened a public debate on the environmental impact of the proposed modernization project of coal-fired thermal power plant Oslomej near Kicevo.

A study on the proposal was made by different groups of experts with the aim to reduce the negative impact on the environment by TPP Oslomej. The study examined the options of using high quality imported coal as well as the lower quality domestic coal available in the vicinity of the plant. The proposal will allow the creation of well balanced domestic power production site that would work at an affordable costs, independent of changes in the world market, while the operational life of the plant would be extended by additional 30 years. It would also make the plant more efficient and would reduce emissions of SOx, NOx and dust particles in order to meet the EU standards.

The project for the modernization of TPP Oslomej envisages an investment of some 126 million euros for the replacement of old steam turbine with a new one able to burn 350,000 tons of coal per year. The modernization also includes the emissions reduction.

TPP Oslomej is the first TPP in Macedonia, put in operation in 1980, with output of 125 MW. The plant is currently supplied with lignite from nearby Oslomej coalmine.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Lower wind and costly gas lift SEE power prices 11/9, but Serbia decouples

Southeast European day-ahead electricity prices strengthened on Friday as weaker wind generation, firm gas costs and reduced imports tightened the regional balance, while Serbia decoupled sharply from neighbouring markets. Hungary’s HUPX baseload price rose €5.60/MWh to €208.98/MWh, almost matching Romania...

Romania’s Cernavoda nuclear restart delayed by low Danube levels

Romania is dealing with a prolonged nuclear outage at the Cernavoda plant, with persistently low Danube river levels delaying restart conditions. Both reactors have been offline since Aug. 13. Unit 1 had already stopped in July before unit 2...

Econergy launches 70 MW battery with Parau 1 solar in Romania

Renewable developer Econergy has placed a 70 MW/141 MWh battery into commercial operation alongside its Parau 1 solar plant in Romania. The project is positioned as a merchant solar-storage combination. The investment in the combined development reached around €85...
Supported byVirtu Energy