Pljevlja thermal output covers most of EPCG generation during Montenegro drought

Coal-fired share rises as hydropower weakens

Montenegro’s Pljevlja supplied 65% of electricity generation for state utility EPCG during the summer period as drought reduced hydro output. Between June and August, the Pljevlja thermal power plant provided around 65% of the electricity generated by EPCG. Poor hydrology increased the country’s reliance on coal-fired production.

The plant’s generation was supported by lignite from a nearby mine. EPCG operates the mine as part of an integrated mining and generation complex, enabling continuous operation during the period.

Generation volume, operating level and market value

Across the three months, the plant generated approximately 442,000 MWh. It operated at an average load of around 200 MW, producing close to 4,800 MWh per day. EPCG placed a value on the output at more than €51 million.

EPCG said buying the same volume on Hungary’s HUPX exchange at prevailing prices would have cost about €57.4 million. The comparison was based on the company’s assessment of market pricing for equivalent electricity volumes.

Hydrological volatility and supply options over summer

The thermal plant’s role became more significant as dry conditions lowered output from Montenegro’s hydroelectric fleet. Hydropower is normally a dominant element in the country’s generation mix. As reservoir conditions deteriorated, Pljevlja continued to provide domestic baseload generation.

The summer performance also reflected a short-term security-of-supply dilemma for Montenegro. The country increases renewable capacity while remaining highly exposed to hydrological volatility that can affect generation availability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

World Bank-backed €50 million programme targets district heating in Pljevlja

Pljevlja transition programme and heating measures Montenegro is preparing an approximately €50 million World Bank-backed investment programme for Pljevlja. The effort targets district heating, cleaner household energy and efficiency measures as the country begins building infrastructure for an eventual transition...

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...