Supported byClarion Energy
HomeElectricityPljevlja thermal output...

Pljevlja thermal output covers most of EPCG generation during Montenegro drought

Coal-fired share rises as hydropower weakens

Montenegro’s Pljevlja supplied 65% of electricity generation for state utility EPCG during the summer period as drought reduced hydro output. Between June and August, the Pljevlja thermal power plant provided around 65% of the electricity generated by EPCG. Poor hydrology increased the country’s reliance on coal-fired production.

The plant’s generation was supported by lignite from a nearby mine. EPCG operates the mine as part of an integrated mining and generation complex, enabling continuous operation during the period.

Generation volume, operating level and market value

Across the three months, the plant generated approximately 442,000 MWh. It operated at an average load of around 200 MW, producing close to 4,800 MWh per day. EPCG placed a value on the output at more than €51 million.

EPCG said buying the same volume on Hungary’s HUPX exchange at prevailing prices would have cost about €57.4 million. The comparison was based on the company’s assessment of market pricing for equivalent electricity volumes.

Hydrological volatility and supply options over summer

The thermal plant’s role became more significant as dry conditions lowered output from Montenegro’s hydroelectric fleet. Hydropower is normally a dominant element in the country’s generation mix. As reservoir conditions deteriorated, Pljevlja continued to provide domestic baseload generation.

The summer performance also reflected a short-term security-of-supply dilemma for Montenegro. The country increases renewable capacity while remaining highly exposed to hydrological volatility that can affect generation availability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...
Supported byVirtu Energy