Supported byClarion Energy
HomeSEE Energy NewsKorita wind project...

Korita wind project gains CGES grid agreement; construction permitting still pending

CGES connection agreement for 88 MW Korita project

Montenegro’s 88 MW Korita wind project has obtained a grid-connection agreement from transmission system operator CGES, addressing one of the main administrative hurdles for the proposed development near Bijelo Polje. The agreement follows a period in which the project faced permitting constraints related to the status of the CGES connection arrangement. The project is being developed by Vjetro Park Korita.

The development is expected to require investment of approximately €132 million. This implies an indicative development cost of €1.5 million per MW, consistent with onshore wind projects that require work associated with mountainous terrain, road access and substantial grid requirements. Korita is planned across approximately 162 hectares near the village of the same name.

Project configuration and scheduled commissioning

The scheme would include 11 wind turbines, implying an average turbine rating of around 8 MW. Commercial operation is currently scheduled for 2030. The timeline leaves additional steps before physical works can start, even after securing the grid-connection agreement.

The connection agreement was signed after an administrative setback connected to the construction-permit process. Montenegro’s Ministry of Spatial Planning rejected the developer’s construction-permit application on 18 June 2026, partly because a CGES connection agreement had not yet been concluded. The grid agreement was signed five days later, resolving that specific deficiency without automatically reversing the permitting decision.

Environmental approval and remaining procedural steps

The Environmental Protection Agency approved the project’s environmental impact assessment in December 2025. Additional planning, technical and construction procedures must still be completed before physical works can begin. The next stage involves aligning the connection design with the renewed permitting process.

Further work is also required to convert environmental approval into executable construction documentation. The project’s economics are expected to depend on the final grid-connection scope, access-road and turbine-transport requirements, wind-resource validation and the commercial route to market. With an operating date set for 2030, there is exposure to equipment prices, financing costs and potential changes to balancing and market-integration rules.

The CGES agreement improves bankability but does not yet make the project construction-ready. Alignment of connection design with permitting steps remains a key requirement before construction can proceed.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...

Montenegro imports nearly 30% of electricity needs in 2025

Montenegro relied on imports for almost 30% of its electricity needs in 2025, with net imports covering almost 30% of total electricity requirements. The figures point to continued exposure to regional wholesale markets alongside a largely renewable domestic generation...

Montenegro electricity import bill below €42 million amid Italy interconnector plans

Montenegro has reduced its electricity-import bill to less than €42 million so far in 2026, according to energy officials. The improvement follows spending of almost €182 million during last year’s prolonged Pljevlja overhaul. Energy Minister Admir Šahmanović said the...
Supported byVirtu Energy