Montenegro advances Korita wind power project with environmental approval

The Korita wind power project, located in the municipality of Bijelo Polje, has received a significant boost as the Environmental Protection Agency granted environmental approval. This decision follows the successful completion of an environmental assessment process, paving the way for a wind farm with a total installed capacity of 72.6 MW in the village of Korita.

The comprehensive environmental impact study conducted for the project adhered to all legal requirements and proposed measures designed to prevent, mitigate, or eliminate potential adverse effects on the local environment. The investor is obligated to strictly follow these prescribed measures throughout the construction and operational phases, as well as during any incidents that may occur. Continuous environmental monitoring will be a critical component of this undertaking.

The planned wind farm will consist of 11 turbines strategically placed across various sites, primarily at altitudes exceeding 1,500 meters to capitalize on optimal wind conditions. The construction will cover approximately 162 hectares, while the actual footprint of the turbines will occupy around 3.3 hectares once they are operational.

Additionally, the project includes the development of a new 400 kV transmission line that will connect the forthcoming Korita substation to the existing Ribarevine switching station over a distance of approximately 27.8 kilometers. Furthermore, plans are in place for a solar power plant at the Korita site, which has already received prior environmental approval and will feature a transformer station that will cater to both the wind farm and the new transmission line connection.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Montenegro’s electricity exporters need stronger PPAs to secure Italian market revenues

The Adriatic interconnector gives Montenegro's renewable generators access to Italian buyers, but investment returns depend on carbon treatment, delivery profiles and the fallback provisions built into individual export agreements. Montenegro's electricity interconnection with Italy offers renewable energy investors access to...

Montenegro construction permit issued for 88 MW Korita wind farm near Bijelo Polje

Montenegro has issued a construction permit for the 88 MW Korita wind farm near Bijelo Polje, moving the project towards implementation. The authorisation was granted following completion of planning and environmental approval procedures. The permit was issued to local...
Supported byVirtu Energy