North Macedonia produced 462,653 MWh of electricity in May 2026, up 3.8% year on year. The increase coincided with higher hydropower and wind generation alongside lower thermal output. Gross electricity consumption reached 479,603 MWh, with domestic production covering 96.5% of demand.

Imports totaled 87,978 MWh, compared with 109,220 MWh in May 2025. Exports rose to 71,028 MWh from 67,840 MWh. The figures indicate a reduction in net imports versus the previous year’s month.

Thermal generation declines while hydro and wind rise

Thermal power plants generated 146,647 MWh, accounting for 31.7% of total output. Thermal generation fell 13.6% year on year. The decline reflects continued pressure associated with North Macedonia’s ageing lignite fleet and domestic coal-supply system.

Hydropower output increased by 33.2% to reach 138,015 MWh. Hydropower represented 29.8% of total electricity generation in the month. Wind farms supplied 31,435 MWh, equivalent to 6.8%, after recording annual growth of 50.6%.

Solar and biogas contribute alongside seasonal renewables

Solar plants and prosumers generated 143,419 MWh, equal to approximately 31% of total electricity output. Solar production was nevertheless 2.5% lower than in May 2025. The change was linked to weaker irradiation or differences in the reporting perimeter and operating conditions.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Envision selected for turbines in Stip wind project first phase, North Macedonia

Alcazar Energy Partners has reached financial close for the Stip wind project in North Macedonia. The first phase totals 131.25 MW and has moved toward construction after securing financing and selecting Envision Energy as turbine supplier. The project is...

North Macedonia advances €119 million storage and grid upgrade as flexibility takes over from coal

North Macedonia is preparing a combined €119 million investment in battery storage and grid digitalisation, signalling a shift in the country’s energy transition from replacing coal generation toward building the flexibility and system-control capabilities needed to operate with a...

Serbian electricity faces €78/MWh CBAM cost as EU tightens actual-emissions rules

Serbia’s electricity exports to the European Union face a potentially significant cost disadvantage under the Carbon Border Adjustment Mechanism (CBAM), with an indicative charge of around €78.37/MWh when the national default emissions factor is applied. Such a cost could...
Supported byVirtu Energy