Supported byClarion Energy
HomeElectricityHungary, Country ran...

Hungary, Country ran out of available capacity to connect new renewable energy projects to the electricity transmission network

Hungary ran out of available capacity to connect new renewable energy projects to the electricity transmission network, much to the dismay of RES investors. Namely, in early May, Hungarian electricity transmission system operator MAVIR set the amount of available RES capacity for connection to the network to zero MVA.

The current available capacity allocated to high- voltage transformer stations is also zero, which means that new connection requests cannot be accepted in the tender process. Instead, new connection requests have to be submitted according to an individual procedure, which is more complex and requires that those who connect to the network bear the costs of the connecting infrastructure, including transformer stations.

There were some fundamental changes in the Hungarian electricity market in the last decade. In terms of electricity generation, there has been a shift from a few large producers that were typical in the past to highly decentralized production consisting of many small producers. Meanwhile, the accelerated return on investments in solar projects has dramatically increased demand for network connection capacity, while the “first come, first served” capacity allocation approach has become inadequate.

The Hungarian electricity system currently has about 3,000 MW of installed capacity in solar energy. The installed solar capacities have increased tenfold in the last five years, and further expansion of solar energy in households is expected, where the capacities could double in a year or two. This means that the Hungarian electricity system, in addition to 3,000 MW of renewable capacity already in operation, still has at least 5,000 MW in demand for the connection of new RES projects.

However, MAVIR argues that the current lack of connection capacity does not mean stopping the development of green energy production, and the targets set for 2030 could be achieved earlier than planned, within three to five years.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary tenders 702 MVA grid capacity for new wind projects

Hungary has launched a tender for 702 MVA of grid connection capacity reserved for new wind projects. The allocation is intended to reopen access to grid capacity after a period in which wind development remained largely frozen while solar...

Hungary tenders 702 MVA grid capacity for new wind farm connections

Hungary has released 702 MVA of grid capacity for new wind projects and opened a tender for wind farm grid connections. The offering provides developers with 702 MVA of combined network capacity as the country seeks to restart wind...

Hungary’s higher gas use and imports strengthen its power price premium

Hungary remained one of Southeast Europe’s most expensive electricity markets in Week 34, as a sharp increase in thermal generation coincided with a substantial rise in net electricity imports. The combination points to supply-side economics, rather than stronger demand,...
Supported byVirtu Energy