Supported byClarion Energy
HomeElectricityHungary, Country ran...

Hungary, Country ran out of available capacity to connect new renewable energy projects to the electricity transmission network

Hungary ran out of available capacity to connect new renewable energy projects to the electricity transmission network, much to the dismay of RES investors. Namely, in early May, Hungarian electricity transmission system operator MAVIR set the amount of available RES capacity for connection to the network to zero MVA.

The current available capacity allocated to high- voltage transformer stations is also zero, which means that new connection requests cannot be accepted in the tender process. Instead, new connection requests have to be submitted according to an individual procedure, which is more complex and requires that those who connect to the network bear the costs of the connecting infrastructure, including transformer stations.

There were some fundamental changes in the Hungarian electricity market in the last decade. In terms of electricity generation, there has been a shift from a few large producers that were typical in the past to highly decentralized production consisting of many small producers. Meanwhile, the accelerated return on investments in solar projects has dramatically increased demand for network connection capacity, while the “first come, first served” capacity allocation approach has become inadequate.

The Hungarian electricity system currently has about 3,000 MW of installed capacity in solar energy. The installed solar capacities have increased tenfold in the last five years, and further expansion of solar energy in households is expected, where the capacities could double in a year or two. This means that the Hungarian electricity system, in addition to 3,000 MW of renewable capacity already in operation, still has at least 5,000 MW in demand for the connection of new RES projects.

However, MAVIR argues that the current lack of connection capacity does not mean stopping the development of green energy production, and the targets set for 2030 could be achieved earlier than planned, within three to five years.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungarian power prices surge as weak wind drives Southeast Europe higher

Hungarian electricity prices jumped nearly 12% for Tuesday delivery, driving a broader increase across Southeast Europe as a sharp decline in forecast wind generation and higher electricity demand increased the region’s reliance on imports, while German power prices moved...

Solar growth in Hungary leaves businesses exposed to imported power costs

Hungary’s rapid increase in solar generation has not eliminated reliance on imported electricity, according to economic research institute GKI. The institute said the outcome leaves companies exposed to higher power costs when domestic renewable output drops. The assessment points...

Hungary stockpiles 4.8 billion cubic metres for a 96-day winter gas buffer

Underground inventories ahead of the heating season Hungary has accumulated more than 4.8 billion cubic metres of natural gas in underground storage facilities, enough to cover approximately 96 days of total winter demand. The Ministry of Economy and Energy says...
Supported byVirtu Energy