Supported byClarion Energy
HomeSEE Energy NewsHrgud 60-MW wind...

Hrgud 60-MW wind farm tender halted by complaint in Bosnia and Herzegovina

A formal complaint has stopped the latest procurement for the 60-MW Hrgud wind farm in Bosnia and Herzegovina, extending delays for one of Republika Srpska’s longest-running renewable-energy projects. The procurement cannot proceed on its original timetable until the objection is resolved.

ERS launches €95 million tender near Berkovici

State-owned utility ERS launched a €95 million tender in late August for the project near Berkovici. The tender was issued almost 11 years after ERS obtained the concession for Hrgud. The planned wind farm is expected to generate about 160 GWh annually.

EPC+F procurement requirements for bidders

The procurement is structured under an EPC+F model. The selected contractor is required to provide engineering, equipment, construction and financing. Bidders must also show experience delivering at least one wind farm of 30 MW or more, valued at at least €25 million excluding VAT, during the previous five years.

Bidders are further required to demonstrate experience with substations and transmission lines as part of the qualification process.

Complaint filed 12 days after tender launch

ERS received a formal complaint about the procedure only 12 days after launching the tender. The utility confirmed that the appeal process had begun following receipt of the objection. As a result, the procurement remains paused pending resolution.

The setback arrives as ERS had taken one of its most concrete steps toward moving Hrgud from prolonged development into construction.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy