Greece: TPP Agios Dimitrios phase-out

Lignite-fired thermal power plant Agios Dimitrios is located in Kozani in northern Greece. TPP is operated by Public Power Corporation (PPC). Four units of this TPP will be phased out as of 1 July and should cease operation well before 2022, when the facilities are officially scheduled to shut down as part of Greece’s decarbonization effort.

For now, units I to IV of TPP Agios Dimitrios will only be available during winter season to cover district heating needs. However, these units will not be used for electricity generation.

On the other hand, a desulphurization facility, which is currently being completed Agios Dimitrios’ unit V is expected to prolong the life of this unit as the effort’s results should meet EU emission limits.

According to initial timetable of gradual withdrawal of lignite-fired units operated by PPC, Kardia I and II, each with a capacity of 275 MW, Amynteo I and II, each with 273 MW will be withdrawn by the end of 2020, Kardia III and IV (280 MW each) by the end of 2021, Megalopoli III (255 MW) by the end of 2022, Agios Dimitrios I and II (274 MW each) by the end of 2023, Agios Dimitrios III and IV (283 MW each) by the end of 2025, Agios Dimitrios V (342 MW) by end of 2027 and finally Meliti I (289 MW) and Megalopoli IV (256 MW) by end of 2028. TPP Ptolemaida V, PPC’s lignite-fired power plant which is still under construction, will enter the system in 2022 and produce until 2028. Ptolemaida V could then take on some sort of back-up role beyond 2028, as a converted gas-fired unit.

 

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy