Greece: After five years, gas-fired TPP Megalopoli V operates at full capacity

After five year of production well below its capacity, Public Power Corporation (PPC) has started operating its gas-fired thermal power plant Megalopoli V at full capacity (811 MW).

It is estimated that this restriction cost PPC around 200 million euros.

Electricity transmission system operator ADMIE gave PPC the approval for full-scale production, after an extended period of pressure applied by the company. Previously, PPC was forces to operate the unit at 60 % of its capacity, namely 500 MW, because, according to ADMIE, the transmission network in the region could not cope with more electricity produced.

Trial operation of gas-fired Megalopoli V started in April 2015, but PPC had never been given permission to increase production by additional 311 MW to reach full capacity.

Meanwhile, PPC’s lignite-fired Megalopoli III and IV units were either shut or operated well below full capacity as a result of CO2 emission right costs. This will also enable PPC to completely shut down 250 MW Megalopoli III unit.

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy