Greece, ADMIE will receive a total of 195 million euros in support from Recovery and Resilience Fund

Two network projects developed by Greek electricity transmission system operator ADMIE will receive a total of 195 million euros in support from the country’s Recovery and Resilience Fund.

The projects in question include the fourth and final stage of the Cyclades interconnection to the mainland and the reconstruction of the  Koumoundourou high-voltage substation along with a 400kV transmission line connecting the facility with the Corinth high-voltage substation.

The combined cost of the two projects is 482 million euros. The fourth phase of the Cyclades interconnection, budgeted at 393 million euros, is expected to receive 165 million euros from the Fund, while the Koumoundourou high-voltage substation reconstruction, whose budget is
estimated at 89 million euros, is expected to receive 30 million euros in financing.

Last month, ADMIE said that the investments made in the first nine months of 2021 in the development of key network projects, including
island interconnections, have reached 241.8 million euros, which is by over 100 million euros more compared to the same periods since 2017,
when the operator split from the Public Power Corporation (PPC).

From 2018 to date, ADMIE’s investments in electricity network projects amounted to 1.12 billion euros, which is more than double compared
to 2013-2016 period, when investments reached 489 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy