Supported byClarion Energy
HomeHydroEPCG tenders supervision...

EPCG tenders supervision contract for Otilovići small hydropower plant

Montenegro’s state-owned electricity company EPCG has launched a tender for construction supervision of the Otilovići small hydropower plant. The project is intended to move a delayed development into a more structured construction phase. The supervision contract is valued at approximately €100,000, excluding VAT. Offers are due by 27 July 2026.

Scope and timing of the supervision tender

The selected consultant will oversee the contractor’s work and verify quality and quantities. The role also includes monitoring compliance with the design and supporting technical acceptance of the completed plant. The tender documentation places emphasis on supervision activities during construction rather than post-completion services.

EPCG awarded the design-and-build contract to Montenegrin company Vigoris Ecotech at the beginning of the year. The plant is planned for construction on the Ćehotina River near Pljevlja. It will use water associated with the existing Otilovići reservoir.

Turbine configuration and expected output

The facility will include two horizontal Francis turbines with a combined capacity of 3.2 MW. EPCG expects annual generation of approximately 11 GWh. This corresponds to a capacity factor of about 39%.

EPCG estimates that the plant’s output will be sufficient to cover annual electricity consumption of roughly 1,800 households. The project information also links the scheme’s production profile to its use of water connected to the existing reservoir system.

Concession framework and coordination requirements

The Otilovići project is implemented under a concession agreement signed with the Montenegrin Government in 2022. Its timetable has been extended several times after difficulties in selecting a contractor delayed construction start. EPCG’s published materials describe the current stage as progressing through a more defined construction phase.

The supervision work is expected to be critical given the interfaces between civil works, hydraulic equipment, turbines, electrical systems and grid connection. Environmental-flow obligations and reservoir operating requirements are also expected to be reflected in testing and commissioning. The project’s location near an operating dam and water-supply system requires technical coordination during implementation.

Indicative investment range and CAPEX disclosure

An assumed hydropower investment range of roughly €2 million–€4 million per MW implies a total capital envelope in the region of €6 million–€13 million. The final figure is described as dependent on how much existing infrastructure can be reused. EPCG has not provided a complete current CAPEX figure in the published project information.

EPCG states that Otilovići would not materially alter Montenegro’s national generation balance on its own. The scheme is positioned as adding domestic renewable output near an established water asset while providing another dispatchable plant within a system sensitive to hydrology and electricity-import prices.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro Requires Full Study for 120-MW Cevo Solar Plant

Montenegro’s Environmental Protection Agency has required Permonte to prepare a full environmental impact assessment for its proposed 120-MW Cevo solar development near Cetinje. The project cannot advance through the environmental approval process until its potential impacts have been assessed....

EPCG Appoints Supervisor for 3.2 MW Otilovići Plant

Montenegro’s utility EPCG has appointed local engineering company Sistem-MNE to oversee construction of the 3.2 MW Otilovići small hydropower plant near Pljevlja. Sistem-MNE was the only bidder in the tender. Its offer of €100,000 excluding VAT matched EPCG’s estimated...

Montenegro and Italy step up preparations for electricity market coupling

Montenegro and Italy are advancing preparations for the integration of their wholesale electricity markets, although regulatory requirements mean coordinated trading is unlikely to begin in the near term. Montenegrin energy regulator REGAGEN estimates that the formal market-coupling procedure could take...
Supported byVirtu Energy