Croatia, Nordex to supply turbines for 50 MW wind project

German wind turbine manufacturer Nordex said that it has won the contract for the supply and installation of ten N149/4.X turbines for a 50 MW wind project in Croatia.

The statement from the company said that the wind farm will be built in Gracac municipality, Zadar county, without disclosing any information about the project’s investor.

The signed contract envisages the start of installation of wind turbines in early 2023, with the completion of the process by the end of the same year. In addition, Nordex has also signed a 20-year contract for maintenance of the turbines, which includes an option to extend service of the turbines for a further 10 years.

This is the second order for Nordex’ wind turbines this year in Croatia. In February, the company signed a contract for 25 N149/5.X turbines for 137 MW wind farm.

Currently, Nordex has 312 MW of wind installed capacity in Croatia, With the addition of these two new order, its capacity will increase to almost 500 MW.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...

Croatia launches €38 million household clean-energy grants with battery storage

Croatia opened applications on Tuesday for a €38 million household clean-energy programme that includes support for battery storage for the first time. Authorities said the measure is intended to shift more rooftop solar output into evening demand periods. The...

Croatia records highest summer hourly demand as evening peak surpasses winter

Croatia’s electricity demand reached a record summer hourly level of 3,400.5 MWh in August, exceeding both the country’s previous summer maximum and the latest winter peak. The highest point occurred at around 21:00, after most photovoltaic output had disappeared...