Croatia: Ernestinovo substation malfunction denied

Due to unplanned high flows of electricity from the southeast to the west of Europe, on 8 January 2021, at 14:04 CET, the high voltage switch in the Ernestinovo substation was switched off due to the correct operation of the overload protection. In this chain reaction, a series of transmission line outages occurred in Serbia, Romania and Croatia, which ultimately led to the division of the European electricity system into two parts.

Croatian electricity transmission system operator HOPS denies the information published in some media that a malfunction occurred in the Ernestinovo substation near Osijek three weeks ago, which could have cause blackouts throughout Europe.

HOPS operations staff reconnected the two separated European synchronous areas by switching off the switch in the Ernestinovo substation one hour after the moment of separation.

The European electricity system is prepared for such and similar disruptions, and is capable of rapid operation of regulatory and protection systems to limit the operation of disruptions and thus prevent interruptions in electricity supply. HOPS noted that the European electricity system has never been threatened by a complete or limited breakdown that would cut off electricity supply in Europe.

The causes, chronology and consequences of the incident are being investigated at European level, and a final report is expected within the envisaged period of 6 months. HOPS actively participates in the analysis of events with colleagues from other European transmission system operators, and is a member of a special expert group that prepared a press release published on the website of the Association of European Transmission System Operators (ENTSO-E).

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Croatia extends regulated petrol and diesel price caps for another seven days

Croatia will keep regulated petrol and diesel prices unchanged for another seven days as wholesale fuel costs rise. The measure relies on further reductions in excise duties and supplier margins to offset higher wholesale costs. The government said the...

Croatia launches €38 million household clean-energy grants with battery storage

Croatia opened applications on Tuesday for a €38 million household clean-energy programme that includes support for battery storage for the first time. Authorities said the measure is intended to shift more rooftop solar output into evening demand periods. The...

Croatia records highest summer hourly demand as evening peak surpasses winter

Croatia’s electricity demand reached a record summer hourly level of 3,400.5 MWh in August, exceeding both the country’s previous summer maximum and the latest winter peak. The highest point occurred at around 21:00, after most photovoltaic output had disappeared...
Supported byVirtu Energy