Supported byClarion Energy
HomeSEE Energy NewsBosnia: BH-Gas filed...

Bosnia: BH-Gas filed a countersuit against Croatian contractors Monter and GP Put

Gas company BH-Gas has filed a countersuit against the consortium of Croatian companies Monter and GP Put, which were contractors on the project for the gasification of Middle Bosnia Canton (MBC), to the Sarajevo Arbitration Court.

According to the statement from the company, with this countersuit it seeks compensation for damages in excess to 6 million euros due to poor workmanship on the gas pipeline, as well as compensation for lost profit.

The statement said that the consortium of Croatian companies Monter and GP Put has signed in January 2012, 20 million worth project for the gasification of MBC which included the construction of gas pipeline. The contract was terminated in March 2014 due to deficiencies in performed construction works.

The Government of the Federation of Bosnia and Herzegovina (FBiH) will also make request to the Sarajevo Canton Prosecutor’s Office in order to inspect all the circumstances in relation with the construction of Zenica-Travnik gas pipeline, especially due to the fact that the initial cost of the project was around 15 million euros, but the final price exceeded 20 million euros, transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

SEE power prices ease as imports increase, while Serbia defies regional trend

Southeast European day-ahead electricity prices declined across most markets for Wednesday delivery, narrowing Hungary’s premium over Germany. At the same time, higher gas and carbon costs continued to support firmer forward power prices. Serbia moved against the broader regional trend,...

North Macedonia’s electricity trading jumps 74% as September prices rise

Electricity traded on North Macedonia’s MEMO day-ahead exchange rose 74% year on year to 179.2 GWh in September, pointing to increased participation and growing use of the organised electricity market. Despite the strong annual increase, trading volumes fell 10.3% from...

Serbia plans North Macedonia gas interconnector construction start, aiming Q1 2028

Pipeline scope and early works near Vranjska Banja Serbia is targeting early 2028 completion for its gas interconnector with North Macedonia, with construction planned to start and reach completion in the first quarter of 2028. Initial works near Vranjska Banja...
Supported byVirtu Energy