Bosnia and Herzegovina: RiTE Ugljevik plans €15.5 million share issuance to settle debt with Slovenian HSE and address accumulated losses

The management of the thermal power plant and coalmine (RiTE) Ugljevik, a subsidiary of the state-owned power utility Elektroprivreda Republike Srpske (ERS), is planning a share issuance to raise 15.5 million euros to settle part of its obligations to the Slovenian power company HSE. This proposal will be presented at the shareholders’ assembly scheduled for October 8, 2024. The raised funds will be used to pay off part of the debt resulting from an arbitration ruling, which will help reduce the company’s total liabilities and improve its financial capacity and creditworthiness.

The share issuance aims to partially address the principal debt owed to HSE, which amounts to 67 million euros. RiTE Ugljevik has agreed to repay this debt over the next seven years in 14 equal installments, with the first one already paid on June 30, 2024. However, the company still faces unresolved obligations related to an additional 67 million euros in accrued interest.

At the same meeting, shareholders will also consider a proposal to reduce the company’s capital to cover accumulated losses exceeding 90 million euros. Following the procedure, RiTE Ugljevik’s capital is expected to stand at 34.6 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hrgud 60-MW wind farm tender halted by complaint in Bosnia and Herzegovina

A formal complaint has stopped the latest procurement for the 60-MW Hrgud wind farm in Bosnia and Herzegovina, extending delays for one of Republika Srpska’s longest-running renewable-energy projects. The procurement cannot proceed on its original timetable until the objection...

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...