Bosnia and Herzegovina: Republic of Srpska approves 37 million euro gasification project

The Republic of Srpska (RS) has approved a gasification project for the eastern part of the RS, with an allocated budget of 37 million euros. The Ministry of Finance and the Ministry of Energy and Mining will oversee its implementation, while Sarajevo-Gas from Istočno Sarajevo is responsible for executing the project according to regulations.

The project is divided into three phases, two of which have already been completed:

  • Phase 1: This phase involved constructing a metering and regulation station for Toplane-INS and converting boiler systems to use natural gas instead of environmentally harmful fuel oil. Additionally, the distribution network was expanded in Istočno Novo Sarajevo and Istočna Ilidža. The commissioning of a gas-powered heating plant in Istočno Sarajevo enabled the heating of 70,000 square meters of residential space, 900 apartments, and 30 institutions, with the boiler capacity increased from 8 MW to 20 MW.
  • Phase 2: This phase focused on the construction of the Pale-Jahorina gas pipeline, which supplies natural gas to the municipalities of Pale and Jahorina.
  • Phase 3: The third phase will involve the construction of a main gas pipeline running 48 kilometers from the Jakovice transfer station in Sekovici to Vlasenica, Milici, Igrista, and Han Pijesak. The estimated cost of this phase is 37 million euros.

The gasification project aims to provide natural gas to all public institutions and industrial consumers in the region. It is expected to reduce electricity consumption, potentially creating opportunities to sell surplus electricity at higher prices. Additionally, using natural gas for heating will reduce harmful gas emissions, contributing to environmental protection.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Business electricity prices up 7.7% for medium-sized commercial users in Bosnia

Electricity prices for medium-sized commercial consumers in Bosnia and Herzegovina rose 7.7% year on year in the first half of 2026. The increase exceeded the rise recorded for households over the same period. The data indicate higher electricity costs...

Solar Agroland wins 50-year concession for Bileća 1 solar and storage project

50-year concession in Republic of Srpska Solar Agroland has secured a 50-year concession for the Bileća 1 solar and battery storage project in Bosnia and Herzegovina’s Republic of Srpska. The company’s final layout is still subject to planning decisions and...

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....
Supported byVirtu Energy