Supported byClarion Energy
HomeElectricityBosnia and Herzegovina:...

Bosnia and Herzegovina: Power utility ERS launched a tender for a 14.3-million-euro bank loan

The proceeds of this loan will be used to finance the completion of the concrete lining of the water tunnel of the future 160 MW hydro power plant Dabar, according to Bosnian media.

In July, ERS said that it has completed the drilling of the most important part of the tunnel, a project worth some 61.2 million euros.

In January 2019, Hidroelekrana Dabar, part of ERS’ subsidiary Hidroelektrane na Trebisnjici (HET), has launched an international tender for financing and construction of hydropower plant Dabar, a project worth some 188 million euros. The selected partner will be obliged to build a dam with embankments and an accumulation basin, a surge tank, a machine house, two 200 kV transmission lines and a drainage channel. The preferred model of financing is a monetary loan with a 15-year repayment period and a four-year grace period. The project partner is expected to provide 85 % or more of the financing, while HET will provide up to 15 %. HPP Dabar will remain in HET’s sole possession following the construction which will last four years. In March, Prime Minister of the Republic of Srpska (RS) Radovan Viskovic said that signing of a an agreement on the construction of HPP Dabar with Chinese company has been delayed due to coronavirus outbreak. Future HPP Dabar is a part of hydroelectric system Gornji Horizonti, its planned power output would be 166 MW, its annual electricity generation should be about 250 GWh. It is expected that the construction will be completed within four years.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bosnia gross power generation rises in July on stronger exports

Bosnia and Herzegovina increased gross electricity production to 1,118 GWh in July, up from 1,082 GWh a year earlier. The higher output was supported by stronger hydro and renewable generation. Generation mix shifts with hydro and renewables Thermal plants accounted...

Elektrokrajina to invest €30 million in three-year distribution network reconstruction

Bosnian electricity distributor Elektrokrajina plans to invest about €30 million in a three-year reconstruction of its distribution network. The programme is designed to reduce losses and improve reliability across five cities and 16 municipalities. The works are intended to...
Supported byVirtu Energy