Bosnia and Herzegovina: HPP Visegrad’s June output drops 43% amid ongoing decline in hydropower generation

Hydropower plant Visegrad, operated by “Hidroelektrane na Drini”, a subsidiary of the power utility ERS, generated 33.74 GWh of electricity in June 2025 — a 43% decrease from May’s output of 59.11 GWh. Compared to June 2024, when the plant produced 36.25 GWh, output is also slightly lower.

In 2024, the plant produced a total of 733 GWh, significantly below the 1,224 GWh generated in 2023. Cumulative generation for the first half of 2025 stands at 480 GWh, indicating a continued downward trend.

HPP Visegrad, commissioned in 1989, has an installed capacity of 315 MW (3 x 105 MW) and an average annual production of 1,010 GWh. Its record year was 2010, with 1,283.05 GWh produced.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bosnia gross power generation rises in July on stronger exports

Bosnia and Herzegovina increased gross electricity production to 1,118 GWh in July, up from 1,082 GWh a year earlier. The higher output was supported by stronger hydro and renewable generation. Generation mix shifts with hydro and renewables Thermal plants accounted...

Elektrokrajina to invest €30 million in three-year distribution network reconstruction

Bosnian electricity distributor Elektrokrajina plans to invest about €30 million in a three-year reconstruction of its distribution network. The programme is designed to reduce losses and improve reliability across five cities and 16 municipalities. The works are intended to...