In the first nine months of 2020, coal production of coalmine and thermal power plant (RiTE) Ugljevik amounted to 1,464,562 tons, which is 16 % more than planned for the period (1,264,110 tons).

In the same period, a total of 7,911,000 cubic meters of overburden was excavated, which is 98 % of the planned amount (8,100,000 cubic meters).

RiTE Ugljevik recorded a net loss in the amount of 5.6 million euros in the first nine months of 2020, compared to a loss of around 450,000 euros in the same period last year. The company’s revenues in the first nine months of the year fell by 5 % compared to the same period in 2019 and amounted to 49.7 million euros. Total expenditures rose by 1.8 % to 53 million euros. In late 2019, the newly installed flue gas desulfurization facility at coal-fired thermal power plant Ugljevik, a project worth some 80 million euros, has entered trial operation. The facility was officially put into operation in October.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Putin talks prompt Republika Srpska to seek unchanged Russian gas pricing

Republika Srpska expects Russian gas pricing to remain unchanged, SNSD leader Milorad Dodik said after meetings with Russian President Vladimir Putin in Moscow. Dodik also said Republika Srpska expects Russian gas supplies to continue under existing pricing terms. The...

Business electricity prices up 7.7% for medium-sized commercial users in Bosnia

Electricity prices for medium-sized commercial consumers in Bosnia and Herzegovina rose 7.7% year on year in the first half of 2026. The increase exceeded the rise recorded for households over the same period. The data indicate higher electricity costs...

Solar Agroland wins 50-year concession for Bileća 1 solar and storage project

50-year concession in Republic of Srpska Solar Agroland has secured a 50-year concession for the Bileća 1 solar and battery storage project in Bosnia and Herzegovina’s Republic of Srpska. The company’s final layout is still subject to planning decisions and...
Supported byVirtu Energy