Bosnia and Herzegovina, EPBiH is obliged to pay compensation in the amount of 16.4 million euros

Austrian Strabag has won a dispute before the International Arbitration Court in Brussels, according to which state-owned power utility
EPBiH is obliged to pay compensation in the amount of 16.4 million euros.

The arbitration procedure was initiated by Strabag over the construction of hydropower plant Vranduk on the Bosna river, which was halted in 2017.

According to the ruling, EPBiH is obliged to pay to Strabag 5.7 million euros for the bank guarantee, but also around 410,000 euros for the costs of bank guarantee. The arbitration also determined that EPBiH Austrians has to pay additional 7.8 million euros for other costs. The only item that Strabag was not awarded in the ruling was the loss of profit, because the court determined that they did not prove that they would achieve profit from the concluded contract for the construction of HPP Vranduk.

In January 2016, EPBiH has signed a contract worth 57.4 million euros with the joint venture of Austrian Strabag and Croatian Koncar. The signed turnkey contract includes the development of project documentation, production, delivery and installation of equipment, construction works and testing and commissioning of the plant. The construction of HPP Vranduk was officially launched on 8 September 2016. Construction works on HPP Vranduk were stopped in April 2017, when Strabag asked for additional funds, but EPBiH did not consent to it so Strabag terminated the contract. The Austrian company announced that it will file a lawsuit against EPBiH and will launch an international arbitration.

The reasons for the dispute between the investor EPBiH and the contractor Strabag are related to the cost of the project. Strabag argued that,
although construction works on the plant were launched in September last year, the building permit has not been obtained yet. In addition,
Strabag tried to increase the price of the project by 2.5 million euros due to additional, unexpected costs.

According to the concession agreement from August 2012, EPBiH will design, build and operate the plant. The concession period will be 30 years, with extension option. EPBiH is obliged to pay one -time concession fee of 1.1 million euros, while annual concession fee will be 2.43 % of the annual income. HPP Vranduk will be built on Bosna river near Zenica and will have power output of 19.6 MW, while its annual electricity production should reach 97 GWh. HPP Vranduk will be the first of the 25 cascade HPPs on the Bosna river that should be built until 2025 and it should be commissioned by the end of 2019.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bosnia gross power generation rises in July on stronger exports

Bosnia and Herzegovina increased gross electricity production to 1,118 GWh in July, up from 1,082 GWh a year earlier. The higher output was supported by stronger hydro and renewable generation. Generation mix shifts with hydro and renewables Thermal plants accounted...

Elektrokrajina to invest €30 million in three-year distribution network reconstruction

Bosnian electricity distributor Elektrokrajina plans to invest about €30 million in a three-year reconstruction of its distribution network. The programme is designed to reduce losses and improve reliability across five cities and 16 municipalities. The works are intended to...
Supported byVirtu Energy