Bosnia and Herzegovina: Construction of Sokolac solar power plant to begin by October following permit approval

The construction of the Sokolac solar power plant is anticipated to begin by October, following the issuance of the necessary building permit. Mayor Milovan Bjelica mentioned that the process of converting agricultural land into urban construction land for this €120 million investment is currently ongoing. He expects construction to commence by the end of the construction season, which lasts until October, as the paperwork for the 100 MW solar power plant is nearly complete.

The project faced delays due to a prolonged environmental permitting process, which took six months. However, the location conditions permit has now been issued, clearing the way for construction. The solar power plant will be situated on the Glasinac plateau, benefiting from 1,350 hours of sunshine annually, while only 950 hours are needed for profitability. Cooling devices for the panels are unnecessary due to the area’s average annual temperature of nine degrees Celsius.

EnerState, a Sokolac-based company and a subsidiary of the German Profine group, is the investor. Representatives from EnerState have recently visited China, where they secured an agreement for the installation of the plant’s equipment. The construction and commissioning of the power plant are expected to be completed within 15 months from the day the building permit is obtained.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy