Supported byClarion Energy
HomeUncategorizedWestern Serbia -...

Western Serbia – 400kV Transmission System Upgrade -PFS/FS

 

The project has planned the upgrade of the existing 200 kV network in Western Serbia to 400 kV. The existing overhead lines and substation equipment at Bajina Basta, and the OHL to Valjevo, Obrenovac and Beograd 3, are in extremely poor condition after 50 years of continuous service.

There is also a need to develop a new 400 kV network to accommodate potential projects and to allow for the future development of the electrical system, not only in Serbia and the Western Balkan region, but also connecting into North-East and South-East Europe.
The Pre-Feasibility Study determined the scheme to be analysed in more detail in the Feasibility Study, defining the approach, phasing and sequencing of the transmission system upgrade from 220kV to 400kV and taking into account the environmental and social impact.

The main conclusions were the need to replace the existing lines rather than to refurbish them and the definition of the recommended option. This option was studied in detail during the subsequent feasibility study which carried out the necessary investigations, technical studies, and social and environmental impact assessments. The economic evaluation of the project showed a positive return on the investment.

Source Wbif

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia power prices rise as regional markets retreat from Tuesday’s spike

Serbia’s day-ahead electricity price rose by €18.2/MWh to €195.99/MWh for Wednesday delivery, moving in the opposite direction to sharp declines across most neighbouring markets and narrowing the gap with Hungary to just €2.99/MWh. Hungary’s HUPX benchmark fell by €34.9/MWh to...

EMS begins Bajina Bašta 220 kV to 400 kV upgrade for Trans-Balkan Corridor

Serbian transmission system operator EMS has started upgrading the Bajina Bašta substation from 220 kV to 400 kV, supporting the western segment of the Trans-Balkan Corridor. The project covers the current corridor section valued at around €115 million. The...

Fortis and Inelso to build 30 MW solar with battery storage in Vojvodina

Fortis Energy and Inelso Energy Systems plan to invest about €25.5 million in a 30 MW solar project with battery storage in Serbia’s Vojvodina region. The development is described as ready to build. The project is expected to proceed...
Supported byVirtu Energy