The state-owned company Transnafta has paused its public procurement process for the Hungary-Serbia oil pipeline, following a formal request for legal protection. This decision comes as the project faces scrutiny and challenges that could impact its timeline and execution.

The tender process, which commenced at the end of December, has already undergone multiple revisions. Initially scheduled to wrap up on February 5, the deadline for bid submissions has now been pushed to February 26. The documentation related to the tender has been amended five times, primarily to incorporate clarifications and adjustments to the bidding requirements.

This oil pipeline is projected to cover approximately 113 kilometers within Serbian territory, with plans for it to be entirely underground. It is designed to facilitate an annual transport capacity of 5.5 million tons of crude oil, starting from the Horgos border crossing and concluding at Transnafta’s terminal in Novi Sad.

The planned corridor will traverse several municipalities, including Kanjiža, Senta, Ada, Bečej, Žabalj, and Novi Sad itself, following a predominantly north-to-south alignment. While specific contract values have not been disclosed in the tender documentation, earlier estimates suggested that the Serbian segment could cost up to 157 million euros.

Strategically, this project is deemed crucial for enhancing regional energy connectivity between Hungary and Serbia, reflecting broader efforts to improve energy infrastructure across Southeast Europe.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gazprom gas extension talks in Serbia as NIS sanctions deadline nears

Serbia expects to extend its gas supply arrangement with Gazprom beyond September 30 while Russian deliveries continue. President Aleksandar Vučić said after a call with Russian President Vladimir Putin that an annex should be signed shortly. The extension’s duration,...

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...

Azerbaijan to raise gas deliveries for Niš 350 MW power and 150 MW heat project

Azerbaijan plans to increase gas deliveries to Serbia as the two countries advance a proposed 350 MW power plant and 150 MW heat plant in Niš. Azerbaijani officials said higher volumes would accompany development of the project. The Niš...
Supported byVirtu Energy