Ugljevik plant to stop October 15 amid coal shortages and mounting financial liabilities

Bosnia and Herzegovina’s RiTE Ugljevik coal-fired power plant is expected to cease operations on October 15. The expected shutdown comes as worsening coal shortages...

Ugljevik thermal plant offline after coal supply depletion in Republika Srpska

The Ugljevik thermal power plant remains out of operation after exhausting suitable coal supplies, leaving Republika Srpska without one of its largest domestic electricity...

Bosnia and Herzegovina: RiTE Ugljevik Reports Significant First-Quarter Losses Amid Operational Challenges

The coal mine and thermal power plant (RiTE) Ugljevik is experiencing a substantial financial downturn at the onset of 2026, primarily due to severe...

Bosnia and Herzegovina: Ugljevik Power Plant Settles Financial Dispute with Slovenian Partner

The resolution of a significant financial dispute between the RiTE Ugljevik coalmine and thermal power plant and its Slovenian partner, Elektrogospodarstvo Slovenije (EGS), has...

Slovenia and RS Progress Towards Resolution in Ugljevik Arbitration Dispute

In a significant development in the energy sector, Slovenia and the Republic of Srpska (RS) are making strides toward resolving their long-standing legal dispute...

Republic of Srpska to finalize coal mining rights transfer from Comsar Energy to RiTE Ugljevik

The Government of the Republic of Srpska is poised to finalize a significant decision regarding the transfer of coal mining concession rights from Comsar...

Latest news

Serbia: SEEPEX October power price surges 56% as trading volume climbs

Trading volume on Serbia’s SEEPEX day-ahead electricity market reached 579,308 MWh in October, remaining broadly unchanged from September while increasing 13.2% year on year....

Croatia’s JANAF lifts nine-month profit 5.7% to €35.2 million

In Croatia, oil pipeline operator JANAF raised net profit by 5.7% year on year to €35.2 million in the first nine months of 2026,...

Slovenia advances Mokrice hydropower project towards construction

Slovenia’s government has found that the public benefits of the Mokrice hydropower project outweigh its environmental impact, clearing another major regulatory hurdle for the...

NIS earns €197 million in nine months as refining margins strengthen

Serbia’s oil producer and refiner NIS recorded €197 million in net profit in the first nine months of 2026. EBITDA was €510 million, while...

430-MW Iernut Plant Targets June 2027 Commercial Operation

Romania’s delayed Iernut gas-fired power plant is scheduled to begin commercial operation by the end of June 2027. The revised timetable targets connection of...