Slovenia, NPP Krsko will introduce dry storage of spent nuclear fuel

The management of Slovenia’s sole nuclear power plant Krsko said that the plant will introduce dry storage of spent nuclear fuel, currently the safest way to store such fuel.

The project is worth around 100 million euros, and the storage has a lifespan of 100 years. NEK Board member Sasa Medakovic said that several legal procedures were necessary to introduce dry storage, and that the dry storage building has dimensions of 50 by 70 by 20 meters.

The reinforced concrete slab is 1.75 meters thick, including the perimeter walls that provide flood protection and enable anchoring of storage containers.

The project was prepared for almost eight years, and the storage facility has been verified with a hundred year guarantee. Spent fuel elements will now be stored in a more modern and safer way. Medakovic said that wet storage, a cheaper project, was also considered, but NEK opted for a safer and more modern option.

Disposal of spent nuclear fuel and low and intermediate level radioactive waste is the obligation of Slovenia and Croatia, which are inclined towards a joint solution, Medakovic said, adding that the solution is moving towards deep geological disposal. He added that locations for such disposal are not currently being considered.

The construction of the dry storage building was completed in January. The advantages of dry storage of spent fuel are greater safety compared to the existing method of disposal in a pool, long term cooling without the need for cooling systems (cooling with air flow), minimal required maintenance of the facility, and minimal impact on the environment.

Sign up for updates & special reports

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to...

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Slovenia’s industrial power-sharing model delivers measurable savings as market scales

Slovenia’s electricity-sharing market is beginning to deliver measurable savings for industrial consumers, strengthening the case for an emerging energy-service model focused on allocating existing renewable generation more efficiently rather than building additional generation assets. Slovenian energy technology company SunContract said...
Supported byVirtu Energy