Supported byClarion Energy
HomeElectricitySlovenia net power...

Slovenia net power generation down 9% in May 2026 on lower hydropower

Net electricity generation in Slovenia declined by 9% in May 2026 compared with the same month a year earlier, according to data from the Statistical Office of the Republic of Slovenia. Total net production reached 1,135 GWh. Output was also 6% higher than in April 2026, indicating a monthly rebound.

Generation mix shifts across thermal, hydro, nuclear and renewables

Production trends varied by technology in May 2026. Electricity generated in thermal power plants rose by 2% year-on-year to 73 GWh. Hydropower output fell by 35% to 321 GWh.

Nuclear generation from the Krško plant remained stable at 517 GWh. Wind and solar electricity increased by 34%, reaching 224 GWh. Overall, the technology mix showed contrasting movements between hydro and other sources.

Electricity trade shows higher imports and lower exports

Slovenia imported 869 GWh of electricity in May 2026, which was 9% higher than in May 2025. Exports fell by 9% to 907 GWh. The figures indicate a change in cross-border flows alongside stable nuclear output.

The trade balance reflected these shifts during the month, with imports rising while exports decreased year-on-year. This occurred while domestic generation continued to show mixed performance across technologies.

Consumption and commodity supply decline across most energy products

Electricity consumption also moved in different directions across customer segments. Household demand dropped by 5% month-on-month to 241 GWh. Commercial consumption increased by 4%, reaching 569 GWh.

Supply of energy commodities declined across most categories. Kerosene fell by 22%, natural gas dropped by 18%, and hard coal decreased by 12%, while only coke supply rose by 9%. Compared with May 2025, kerosene, coal, petroleum products, gas and petrol all recorded lower supply levels.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to...

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Slovenia’s industrial power-sharing model delivers measurable savings as market scales

Slovenia’s electricity-sharing market is beginning to deliver measurable savings for industrial consumers, strengthening the case for an emerging energy-service model focused on allocating existing renewable generation more efficiently rather than building additional generation assets. Slovenian energy technology company SunContract said...
Supported byVirtu Energy