More than 25% of electricity used in Serbia in October came from imports, with a market value of around €100 million, or roughly €3 million a day, energy expert Željko Marković said. The purchases add to costs for EPS, Serbia’s electricity company, amid weak hydropower production.

Serbia entered the heating season with maintenance largely completed but remained materially dependent on imported power. Weak hydropower output, rather than a single thermal-unit outage, was identified as the immediate reason for the import need.

Returning coal units from overhaul would not remove the exposure if poor hydrology cuts low-variable-cost hydropower production. In that case, EPS could still need to buy electricity during expensive regional hours. High European gas prices add pressure because gas-fired generation often sets peak power prices across interconnected markets.

Existing storage at Bajina Bašta has reversible hydropower capacity a little above 600 MW. The facility can shift energy, but its capacity is insufficient to offset prolonged supply deficits.

Proposed pumped-storage projects at Bistrica and Đerdap 3 are presented as potential protection against volatile import prices and intermittent renewable output, rather than simply as new generation projects. Serbia’s import exposure is both financial and a security-of-supply risk: the system can remain technically supplied while imports drain value during the most expensive hours.

The strategic challenge is whether Serbia can expand flexibility faster than the gap created by ageing thermal assets, variable hydropower and rising renewable penetration. The import situation strengthens the investment case for pumped hydro, battery energy storage systems, demand response and stronger cross-border hedging, alongside new generation.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Southeast Europe enters 2026-27 winter short of flexibility

Southeast Europe faces a growing power-system flexibility shortage as grids, storage and dispatchable capacity lag behind project growth and rising volatility. Country-level pressures range from heavy imports in Serbia to negative prices in Croatia and faster battery deployment in Bulgaria.

US extends NIS licence to 11 December 2026, keeping refinery operating

The licence extension allows Serbia’s only crude-oil refinery to continue operating, but leaves the country exposed to Russian gas supply and sanctions-related risks.

Montenegro hydro output drops 36.3% as Balkan supply risks rise

Drought is reducing hydroelectric output and constraining nuclear generation across the Balkans, increasing exposure to electricity imports. The pressure highlights the role of diversified generation, storage and interconnection.