Supported byClarion Energy
HomeElectricitySerbia: Revitalization of...

Serbia: Revitalization of Bajina Basta pumped-storage hydropower plant progresses as planned

The second phase of the revitalization of Serbia’s Bajina Basta pumped-storage hydropower plant (HPP) is progressing smoothly, with equipment dismantling completed and testing currently underway. HPP Bajina Basta plays a vital role in the operations of Electric Power Industry of Serbia (EPS) and the country’s national electricity grid. The refurbishment aims to enhance the plant’s efficiency and extend its operational lifespan by several decades.

This modernization project is the most significant initiative within EPS’s broader hydropower infrastructure renewal program. After the successful upgrade of the first generator, improvements in efficiency have already been observed, and similar results are anticipated for the second unit, which is currently undergoing renovation.

The lessons learned and experience gained from the Bajina Basta project are expected to be applied to future upgrades at other hydropower plants in Serbia, including the facilities at Vrla, Potpec, Bistrica, and the planned Djerdap 2 plant. Additionally, the project is setting a precedent for the construction of the new Bistrica pumped-storage facility.

As Serbia’s electricity systems continue to adapt to an increasing share of renewable energy sources, pumped-storage plants like Bajina Basta will become even more crucial for maintaining network stability, ensuring reliable energy supply and supporting grid balancing.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia launches $600 million gas network modernisation with World Bank support

Serbia has secured a $600 million World Bank framework for a gas-system overhaul. The programme is planned as a decade-long modernisation of Serbia’s gas network. It covers pipelines, underground storage and institutional reforms. Financing and initial pipeline focus The first phase...

Serbia’s industrial exporters could help drive the next wave of renewable investment

Serbian industrial exporters could become increasingly important anchor customers for new renewable energy projects as developers seek long-term buyers, while manufacturers look for greater control over future electricity costs and carbon exposure. The traditional corporate PPA connected a renewable generator...

Serbia’s electricity suppliers enter the CBAM-ready industrial power market

Serbia’s electricity supply market is gradually creating space for a more sophisticated industrial energy product, where the value of electricity depends not only on its price, but also on how clearly its origin, contractual chain and emissions profile can...
Supported byVirtu Energy