Serbia: HPP Zvornik reached record in daily electricity production

At HPP Zvornik record daily amount of electricity – 2.835 million kWh, was produced on 3 January. Serbian state-owned power utility EPS said that the effects of the revitalization of hydropower plant Zvornik, which was completed in the beginning of 2020, are already visible.

With the revitalization, the power output of HPP Zvornik’s units was increased by 30 MW, which, in the current hydrological conditions, produce about 20 % more electricity than before. The total installed capacity of the plant after its revitalization is increased to 125.6 MW, which is 30 % more than before.

Revitalization has also contributed to reducing maintenance costs and extending the operational life of the power plant by 40 years. Electricity production is expected to increase by up to 15 % annually, depending on hydrological conditions, which is about additional 70 million kWh per year.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia: SEEPEX power price plunges to €109/MWh as regional markets diverge

Day-ahead electricity prices fell across most Southeast European markets and Hungary on Wednesday, with Serbia recording the steepest decline, while Italy remained close to €225/MWh. The divergence widened regional price spreads despite broadly stable electricity demand. Serbia’s SEEPEX baseload price...

Bulgaria power surplus expands on stronger hydropower and renewables

Production and demand trends to Sept. 6 Bulgaria’s electricity production increased 9.65% year on year to 30.64 TWh between Jan. 1 and Sept. 6, according to data from Bulgaria’s Electricity System Operator. Domestic consumption rose 7.77% to 28.04 TWh over...

Fortis moves 300-MW Serbian solar portfolio to ready-to-build stage

Fortis Energy has advanced a 300-MW portfolio of Serbian solar assets to ready-to-build status, enabling the projects to proceed to equipment procurement and construction. The company said the move covers two separate developments totalling 300 MW. Nocaj and Green...
Supported byVirtu Energy