Serbia: First equipment for Kostolac wind farm delivered

Elektroprivreda Srbije said the first equipment for the 66 MW Kostolac wind farm, including three blades and two tower segments, has arrived at the construction site.

The remaining equipment is scheduled to arrive over the coming months, with all deliveries expected to be completed by the start of October. Installation work will start progressively, EPS said in a statement.

The goal is to build the Kostolac farm, which will be the first wind farm in EPS’s portfolio, by the end of 2024 and to connect it to the grid in early 2025, the statement read.

The project will comprise 20 Siemens-Gamesa wind turbines of 3.3 MW each.

The project is estimated at 144 million euros, with EPS financing 32.2 million euros of total from its own funds, the EU providing a 30 million euro grant and German development bank KfW extending an 80 million euro loan and a 1.8 million euro grant to support it.

The Kostolac wind farm is expected to generate enough electricity to meet the needs of 30,000 households.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPS secures €107.5 million for hydro upgrades and coal-site solar in Serbia

EPS, Serbia’s state utility, has secured approximately €107.5 million to modernise hydropower plants and develop more than 120 MW of solar capacity on land tied to former coal-fired facilities. The financing package combines a €100 million European Investment Bank...

EPS opens renewable M&A channel for Serbian wind, solar and hybrid projects

Serbia’s state-owned power utility EPS has opened a formal channel to acquire or partner with privately developed renewable energy projects of at least 50 MW, creating a potential exit opportunity for developers as grid access, financing and market conditions...

EPS consultancy tender to update procurement for 660 MW Bistrica pumped storage

EPS procurement update ahead of international construction tender Serbia’s state power utility EPS has launched a consultancy tender to revise procurement documents for the planned 660 MW Bistrica pumped-storage hydropower plant before an international construction tender. The existing procurement documentation...
Supported byVirtu Energy