On the Serbian day-ahead exchange SEEPEX on November 02, 2016 (delivery date: November 03, 2016) trading was carried out at the price of 49.04 EUR/MWh for daily baseload. Trading volume was 1,827.4 MWh.

The price of peak energy for daily peak load was 56.84 EUR/MWh and trading volume was 912.2 MWh.

On the Croatian day-ahead power market CROPEX trading was carried out at the price of 51.4 EUR/MWh for daily baseload.

The price of peak energy for daily peak load was at the level of 60.75 EUR per MWh.

Total trading volume was 493.3 MWh.

On the Romanian day-ahead power market OPCOM trading was carried out at the price of 51.62 EUR/MWh for daily baseload.

The price of peak energy for daily peak load was at the level of 59.86 EUR per MWh. Trading volume was 39,181.1 MWh.

During off-peak hours the price was 43.39 EUR per MWh, and trading volume was 35,511 MWh.

On Hungarian day-ahead power market HUPX trading was carried out at the price of 52.14 EUR per MWh for daily baseload.

The price of peak energy for daily peak load was at the level of 60.47 EUR per MWh.

Total trading volume was 56,394.4 MWh.

On Bulgarian exchange IBEX the price for baseload was 46.19 EUR per MWh.

The price of peak energy was 53.09 EUR per MWh, and trading volume was 5,075.9 MWh.

During off-peak hours the price was 39.28 EUR per MWh, and trading volume was 4,700.1 MWh.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Lower wind and costly gas lift SEE power prices 11/9, but Serbia decouples

Southeast European day-ahead electricity prices strengthened on Friday as weaker wind generation, firm gas costs and reduced imports tightened the regional balance, while Serbia decoupled sharply from neighbouring markets. Hungary’s HUPX baseload price rose €5.60/MWh to €208.98/MWh, almost matching Romania...

Romania’s Cernavoda nuclear restart delayed by low Danube levels

Romania is dealing with a prolonged nuclear outage at the Cernavoda plant, with persistently low Danube river levels delaying restart conditions. Both reactors have been offline since Aug. 13. Unit 1 had already stopped in July before unit 2...

Econergy launches 70 MW battery with Parau 1 solar in Romania