Supported byClarion Energy
HomeOilRomania: Rompetrol Rafinare...

Romania: Rompetrol Rafinare invested 16 million USD in two modern reactors at the Petromidia refinery

Rompetrol Rafinare, a member company of the KMG International Group (Rompetrol), introduced two modern reactors into the operational flow of the Petromidia refinery, part of the Middle Distillate Hydrotreating (HDV) unit.

The investment of about 16 million dollars, implemented as part of the recently completed general turnaround, will lead to increased amounts of loaded catalysts. This special equipment is designed and executed for operation at considerable temperatures and pressures in an environment with the presence of hydrogen.

The two reactors, which measure approximately 33 meters in height and weigh approximately 285 tons each, were manufactured in Romania by the Comes company and the installation in the operational flow was carried out by Industrial Montaj.

The role of HDV is the processing/hydrotreating of diesel mixtures resulting from the technological processes of other facilities in the operational flow, to eliminate sulfur compounds and, implicitly, obtain EURO 5 components for the final production of diesel.

Changing the reactors is one of the most important projects implemented during the turnaround. In total, around 85 million dollars were invested in the modernization projects of the Petromidia refinery, the largest profile unit in the country.

In the first three months of 2024, the Petromidia refinery processed 943.000 tons of raw materials, mostly crude oil of Kazakhstan origin. Rompetrol Rafinare is one of the most important contributors to Romania’s state budget, paying over 316 million dollars in the first quarter of the year.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania sets rules for Black Sea wind with 3.1 GW potential

Romania has adopted initial regulations to open its offshore wind sector to investors, with three Black Sea areas offering about 3.1 GW of potential capacity. Transelectrica plans more than EUR 2.2 billion in transmission investment between 2026 and 2035 to support renewable generation and storage.

Rezolv secures up to EUR 367 million for 292.5 MW wind farm

Rezolv Energy secured financing of up to EUR 367 million for its Dunarea East wind farm in Romania, clearing the way for construction. The 292.5 MW project is scheduled to enter commercial operation in early 2029.

Romanian day-ahead power price hits EUR 239.32/MWh in October

Romania's day-ahead electricity price rose 35.87% from September and nearly doubled year on year, while traded volume remained below its October 2025 level. Transaction value climbed as higher prices outweighed limited volume growth.
Supported byVirtu Energy