Romania: Romgaz temporary suspends contract termination for construction of gas-fired unit at Iernut

In late 2020, natural gas producer Romgaz said that it would not grant an extension of the deadline for the completion of the construction of a gas-fired unit at the existing TPP Iernut, which was proposed by project’s contractors – Spanish Duro Felguera and local Romelectro. The agreed deadline for the completion of the project expired on 26 December. The statement from Romgaz said that it will identify the necessary solutions to complete and commission the combined cycle unit at Iernut and will inform of its decision at a later date.

Romgaz said that it has decided to temporary suspend the termination of contract for the construction of a gas-fired unit at thermal power plant Iernut with a consortium of Spanish Duro Felguara and Romanian Romelectro.

The statement from the company said that it has suspended for 14 days the notice on the contract’s termination at the consortium’s request. Within that timeframe, the consortium will submit a proposal about finalizing the works and putting the plant into operation as soon as possible.

In November 2016, Romgaz has concluded an agreement worth 268 million euros (without VAT) with a consortium of Spanish company Duro Felguera and Romanian Romelectro for a turnkey project for the construction of new 430 MW gas-fired power plant within its Iernut thermal power plant. The deadline for the completion of the new combined cycle power plant is 36 months from the effective date of the contract, which shall be within 5 working days from the date the NIP financing is approved. Romgaz took over Iernut thermal power plant in 2013 from Bucharest-based thermal energy producer ELCEN in exchange for deleting a 145 million euros debt. Initially, the plant was supposed to be commissioned in early 2020, but delays have arisen, both as a result of disagreements between partners regarding the provisions of GEO 114/2018 and regarding the increase in construction costs. In May, Romgaz CEO Adrian Volintiru said that the unit will be commissioned by the end of 2020.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania weighs extending household gas protections beyond 2027

Romania may delay the full liberalisation of gas prices for households beyond March 2027, as policymakers weigh the risk of higher bills against the financial and regulatory demands of returning to market-based pricing. Energy Minister-designate Dumitru Chisalita has called...

Fitch Affirms Romgaz at BBB- as Neptun Deep Raises Growth and Debt Risks

Romanian gas producer Romgaz has kept its BBB- rating, with a negative outlook, as expected growth from the Neptun Deep offshore gas development is weighed against heavy investment, regulated prices and risks linked to Romania’s sovereign credit profile. Fitch...

TDI financing for 58 MW Iratoșu solar plant in western Romania

TDI Renewables has secured €25.5 million in financing from Raiffeisen Bank International for its 58 MW Iratoșu solar power plant in western Romania. The project is located in Arad county and is part of a broader development programme that...
Supported byVirtu Energy