Supported byClarion Energy
HomeSEE Energy NewsRomania, Romgaz amounted...

Romania, Romgaz amounted to 23.83 million barrels of oil equivalent in the first nine months of 2022

Hydrocarbon output of Romanian natural gas producer Romgaz amounted to 23.83 million barrels of oil equivalent in the first nine months of 2022, which is 0.67 % less compared to the same period last year.

The amount of extracted gas dropped by 0.51 % and amounted to 23.7 million barrels of oil equivalent. Gas from domestic production delivered to the market dropped by 6.22 % year- on-year to 3.52 billion cubic meters in the January -September 2022 period.

Electricity generation in the first nine months od 2022 totaled 839.5 GWh, which is almost doubled compared to the same period in 2021.

In the third quarter alone, hydrocarbon production amounted to 7.58 million barrels of oil equivalent, which is 1.42 % lower compared to Q3 2021, while the amount of extracted natural gas was 1.172 billion cubic meters (- 1.25 %). Condensate production decreased by 22.95 % to 5.03 million tons of oil equivalent, while electricity generation reached 294.8 GWh, a 32.2 % increase compared to Q3 2021.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy