Romania, OMV Petrom and Tinmar Energy to help EC Oltenia with its restructuring

CEO of Romanian coal-based electricity producer Energy Complex (EC) Oltenia Daniel Burlan said that the company received three offers for the construction of eight solar power plants and one offer for the construction of gas-fired unit at TPP Turceni, all part of its recently approved restructuring and decarbonization plan worth 2.66 billion euros.

Regarding solar power plants, Burlan said that two offers have been accepted, one from OMV Petrom for partnership in the construction of four solar power plants with combined installed capacity of 455 MW, and the other from Tinmar Energy for the construction of four solar power plants with combined capacity of 286 MW.

Tinmar Energy was also selected as a partner for the construction of 475 MW gas-fired unit at TPP Turceni, which would replace the existing coalfired unit (330 MW).

However, there were no offers for the construction of gas-fired units with combined capacity of 850 MW at TPP Isalnita, which are supposed to replace two coal-fired units (330 MW each). Burlan said that the tender will be relaunched by the end of February.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...

Lukoil appoints Eugene Maniakhine to oversee Petrotel refinery restructuring

Lukoil has appointed Eugene Maniakhine to oversee the restructuring of its Petrotel refinery in Romania. The facility entered insolvency proceedings in August 2026 after remaining offline since the previous year. The restructuring process is being handled under Romanian insolvency...

Romania targets Neptun Deep first gas in H1 2027 as execution advances

Romania has narrowed the Neptun Deep first-gas window to the first half of 2027, from a broader timetable previously associated with the €4 billion Black Sea development. The project is expected to bring about 8 bcm/year of production closer...
Supported byVirtu Energy