Romania: New prosumers’s capacity could be limited

The installed capacity of the prosumers’ installations in Romania is approaching the threshold of 8% of the installed power at the national level, a threshold at which the state can intervene to limit it if the distribution network is experiencing problems.

Any restrictive measures to limit prosumers can only be taken after a study is done, according to the president of the Industry and Services Commission in the Chamber of Deputies, Sandor Bende.

According to the latest data, the capacity of prosumers’ installations has exceeded the threshold of 1,000 MW.

The number of prosumers connected to the electric distribution network has reached 78,000.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy