Romania: Hidroelectrica re-launches €106M tender for Brădișor hydropower plant upgrade

Romanian electricity producer Hidroelectrica has re-launched the tender for the refurbishment and upgrade of its 100 MW Brădișor hydropower plant. The company has allocated approximately 106 million euros for the design and execution of the project, after a previous attempt to secure a contractor for around 75 million euros failed due to a lack of bidders.

The tender documentation outlines that the winning bid will be selected based on a scoring procedure, with the highest weight given to the maximum guaranteed power of the turbine.

The Brădișor hydropower plant, which has a project-installed capacity of 115 MW across two Francis turbines, is located on the Lotru River in Vâlcea County. The plant has been operational since 1982.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania expands flexibility market as industrial demand and telecom batteries enter power system

Romania is beginning to turn electricity demand and previously underused backup infrastructure into tradable flexibility, creating new opportunities for aggregators and virtual power plants across Southeast Europe. Two developments illustrate the shift. Transmission system operator Transelectrica activated Romania’s first balancing...

Romania’s power imports surge as renewable generation declines

Romania’s net electricity imports surged 82.08% to 135.72 GWh in the week ending 20 September, as weaker renewable and hydropower generation increased the country’s reliance on electricity from neighbouring markets. Wind and solar generation in Romania fell by 25.9%, while...

Cernavoda output loss expected to continue into October amid low Danube levels

Romania is expected to remain without output from the Cernavoda nuclear plant into October as low Danube levels continue to restrict cooling conditions. The prolonged outage is occurring during a tight regional power market, with increased reliance on cross-border...
Supported byVirtu Energy