Supported byClarion Energy
HomeSEE Energy NewsRomania: Eurowind Energy...

Romania: Eurowind Energy advances Pecineaga wind farm project

Danish renewables developer Eurowind Energy has successfully completed the first phase of its 48 MW Pecineaga wind farm project in Constanta County, Romania. The project is set to be operational by 2025 and will generate green energy sufficient for approximately 48,000 households.

In this initial phase, Eurowind Energy has installed 4 out of 8 foundations for Siemens Gamesa SG 6.6-170 wind turbines, which are the largest wind turbines in Romania. Additionally, essential infrastructure has been constructed, including access roads for logistics, a medium voltage system for efficient energy distribution, and preparations for connecting the wind farm to the electricity network. The first wind turbine is scheduled for installation in October, and the completed wind farm is expected to produce around 176,000 MWh of electricity annually.

In April, Eurowind Energy secured a €65.33 million credit facility for the Pecineaga wind farm’s development. Banca Comerciala Romana (BCR) and Erste Group Bank are jointly financing this investment, each contributing €32.66 million. The loan, which covers 70% of the project’s total development costs, will mature at the end of 2040. Additionally, the banks are providing an €18 million package, including a VAT facility and other supportive financial products for the Pecineaga project.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania sets rules for Black Sea wind with 3.1 GW potential

Romania has adopted initial regulations to open its offshore wind sector to investors, with three Black Sea areas offering about 3.1 GW of potential capacity. Transelectrica plans more than EUR 2.2 billion in transmission investment between 2026 and 2035 to support renewable generation and storage.

Rezolv secures up to EUR 367 million for 292.5 MW wind farm

Rezolv Energy secured financing of up to EUR 367 million for its Dunarea East wind farm in Romania, clearing the way for construction. The 292.5 MW project is scheduled to enter commercial operation in early 2029.

Romanian day-ahead power price hits EUR 239.32/MWh in October

Romania's day-ahead electricity price rose 35.87% from September and nearly doubled year on year, while traded volume remained below its October 2025 level. Transaction value climbed as higher prices outweighed limited volume growth.
Supported byVirtu Energy