In the six counties where it operates – Moldova (Bacau, Botosani, Iasi, Neamt, Suceava and Vaslui), Romanian natural gas and electricity distributor Delgaz Grid, a subsidiary of German company E.ON, has invested more than 680 million euros since 2005 in the modernization of the electricity distribution system. One of the company’s priorities is to automate the electricity distribution infrastructure by installing remote-controlled equipment in stations and transformation units, in medium voltage networks and integrating them into SCADA (data acquisition, remote control and control).

Of the 134 transformer stations that the company operates, 122 have been modernized and integrated (totally or partially) into SCADA. At the end of last year, a program of about 2.5 million euros was completed, running for two years, which aimed at modernizing and integrating 13 transformation stations in SCADA. General Manager of Delgaz Grid Csulak Ferenc said that the results of the investments are visible, the quality of the electricity distribution service, especially ensuring the continuity of the service, has been permanently improved. This year the company has allocated a record investment budget for the electricity segment of almost 89 million euros, 38 % more than in the previous year.

By the end of 2020, about 327,000 smart meters have already been installed in consumers in over 750 localities in Moldova, through successive investment programs. Most units were installed in Bacau and Neamt counties, where about 64 % and 44 % of customers, respectively, benefit from smart metering.

For the period 2021-2028, the company’s goal is to install another 387,000 meters. This means that over 700,000 customers representing 45 % of the total customers connected to the company’s electricity network will have smart meters installed by the end of 2028.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy