Romania: Cernavoda Unit 2 taken offline for technical assessments after smoke incident

Nuclearelectrica, the operator of Romania’s only nuclear power plant at Cernavoda, announced that Unit 2 was taken offline on 25 June in a controlled shutdown. The move was made to allow for further technical assessments and, if necessary, the implementation of corrective measures. The company stressed that all procedures are being conducted according to strict safety protocols and pose no risk to nuclear security, plant personnel, or the surrounding community.

Earlier that day, Unit 2 had resumed operations following a scheduled maintenance outage. The planned downtime included routine servicing and system checks, all of which were completed successfully.

Later on 25 June, smoke was detected—without visible flames—in the administrative area of the facility. Nuclearelectrica promptly located and resolved the issue, confirming that there was no danger related to the incident. Both nuclear reactors continued to function within normal parameters immediately afterward.

The Cernavoda Nuclear Power Plant consists of two 700 MW units, which together account for approximately 20% of Romania’s total electricity generation.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...

Lukoil appoints Eugene Maniakhine to oversee Petrotel refinery restructuring

Lukoil has appointed Eugene Maniakhine to oversee the restructuring of its Petrotel refinery in Romania. The facility entered insolvency proceedings in August 2026 after remaining offline since the previous year. The restructuring process is being handled under Romanian insolvency...

Romania targets Neptun Deep first gas in H1 2027 as execution advances

Romania has narrowed the Neptun Deep first-gas window to the first half of 2027, from a broader timetable previously associated with the €4 billion Black Sea development. The project is expected to bring about 8 bcm/year of production closer...
Supported byVirtu Energy