Romania brings Cernavoda Unit 1 back, restoring 700 MW nuclear capacity

Romania has restarted Cernavoda Nuclear Power Plant Unit 1 following a scheduled maintenance outage, restoring 700 MW of nuclear generation capacity to commercial operation. The unit’s return follows the completion of work that kept the reactor offline for a planned period. Nuclearelectrica said the restart supports Romania’s electricity supply position and system flexibility during times when renewable output declines.

Maintenance outage and grid reconnection

The reactor, operated by Nuclearelectrica, was disconnected from the grid on 10 May for a maintenance programme lasting approximately two months. The scope included preventive and corrective maintenance, mandatory safety inspections, equipment testing, and modernization activities on selected plant systems. These measures were carried out to support continued reliable operation.

Nuclearelectrica stated that all maintenance activities were completed in line with approved technical procedures. The company said the works complied with nuclear safety standards and environmental protection requirements. The restart of the unit followed completion of the programme.

Impact on system balance and operational performance

The return of Cernavoda Unit 1 is expected to improve the balance of Romania’s electricity system. The effect is most relevant during evening peak hours when solar generation decreases while electricity demand remains elevated. Nuclearelectrica said the additional available capacity can reduce reliance on imports and support stability in tighter market conditions.

Unit 1 was commissioned in 1996 and has generated more than 149 million MWh over its operational lifetime. Nuclearelectrica estimates that the reactor’s output has avoided approximately 145 million tonnes of CO₂. The company also reported a capacity factor above 90%.

Nuclearelectrica’s CANDU fleet and fuel production

Nuclearelectrica operates two 700 MW CANDU reactors at Cernavoda Nuclear Power Plant. The company also owns the Nuclear Fuel Factory in Pitesti, which manufactures fuel bundles for CANDU 6 reactors. Its nuclear assets are positioned as part of Romania’s energy strategy supporting security of supply, decarbonisation targets, and electricity-market stability across Southeast Europe.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Renalfa starts 269 MW Horia 2 solar plant in Romania

Renalfa Solarpro Group has begun construction of the 269 MW Horia 2 solar plant in Arad county, Romania. The project marks the first phase of a larger renewable complex combining photovoltaic generation and battery storage. Horia 2 will have...

ENNA Plans 166 MW Romanian Solar Project with 612 MWh Battery

Croatia’s ENNA Group plans to acquire a 166 MW solar project and a 612 MWh battery storage facility near Medgidia in Romania’s Constanța county, expanding its renewable investment programme in Central and Eastern Europe. The project covers around 204 hectares,...

Romania strengthens electricity supply as renewable and thermal output curb import dependence

Romania recorded one of Southeast Europe’s strongest electricity supply performances in Week 42, meeting a substantial increase in domestic demand while significantly reducing its reliance on net imports. Higher wind, hydropower and thermal generation helped strengthen the country’s supply...
Supported byVirtu Energy