Supported byClarion Energy
HomeElectricityRomania: Bankruptcy of...

Romania: Bankruptcy of Termoenergetica

less than a year after it took over the infrastructure (and reportedly the management) of its predecessor, Termoenergetica, the successor of Bucharest’s bankrupt municipal district heating provider RADET, might also go bankrupt.t

ELCEN, heat and electricity producer that delivers hot water and heat to Termoenergetica, claims that the latter has accumulated unpaid bills of over 87 million euros. In its turn, ELCEN has unpaid bills to natural gas suppliers of over 40 million euros. ELCEN could thus register a negative cash flow, which will lead to the impossibility of paying the bills issued by the natural gas supplier. In this context, ELCEN claims that it has already received a notification about the possible cessation of the supply of natural gas in the event of non-payment of financial obligations.

Ovidiu Neacsu from Sierra Quadrant, the judicial manager of ELCEN, said that if this situation is reached, ELCEN will no longer be able to produce the thermal energy necessary for the supply of hot water and district heating in Bucharest. The current situation shows that Termoenergetica took from RADET not only the same management team which put RADET into bankruptcy but also the management model, implemented in the same disastrous way in the new company.

ELCEN is under the control of the Ministry of Energy, while Termoenergetica is controlled by the Bucharest City Hall, led by opposing Social Democrats. Thus, the dispute between the two companies has been strongly politicized in recent years.

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy