Overhaul project on Power Plant TENT, A4 unit just started

 

Unit A4 of the Power Plant Nikola Tesla (TENT) Obrenovac is in regular overhaul cycle, which will last for around 2 months.

Six mills will be reconstructed during 75 days of actitivities. This important project will be completed in cooperation with Hitachi and local company Minel Kotlogradnja (subcontractor), while German bank Kfw secured the financing of the project with its credit line.

According to the main maintenance engineer on TENT A PP, Mr.Milos Vlajic, mills reconstruction started 4 years ago on unit A3. For next year same activities are planed on Unit A5. With this project on A4 this year we will gain on improvement of milling and achieving projected capacities of the mills.

From bigger work on A4 we will complete overhaul on piping system of the boiler. Other activities will include important works on turbine, management control system, electrostatic precipitator controlling etc.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Lower wind and costly gas lift SEE power prices 11/9, but Serbia decouples

Southeast European day-ahead electricity prices strengthened on Friday as weaker wind generation, firm gas costs and reduced imports tightened the regional balance, while Serbia decoupled sharply from neighbouring markets. Hungary’s HUPX baseload price rose €5.60/MWh to €208.98/MWh, almost matching Romania...

Romania’s Cernavoda nuclear restart delayed by low Danube levels

Romania is dealing with a prolonged nuclear outage at the Cernavoda plant, with persistently low Danube river levels delaying restart conditions. Both reactors have been offline since Aug. 13. Unit 1 had already stopped in July before unit 2...

Econergy launches 70 MW battery with Parau 1 solar in Romania

Renewable developer Econergy has placed a 70 MW/141 MWh battery into commercial operation alongside its Parau 1 solar plant in Romania. The project is positioned as a merchant solar-storage combination. The investment in the combined development reached around €85...
Supported byVirtu Energy