North Macedonia proposes higher rooftop solar limits and faster approval process

North Macedonia is preparing to raise the maximum capacity for rooftop solar installations to 10 kW for households and 70 kW for businesses, up from the current limits of 6 kW and 40 kW. The draft legislation also introduces strict timelines for permitting and grid connection.

Under the proposal, authorities will be required to issue permits for systems up to 100 kW within one month of receiving an application. This deadline applies to both individual prosumers and collective energy communities. For grid connections, the distribution operator will have one month from confirming complete documentation to connect the installation.

If connecting at the requested location is not possible, the operator must inform the applicant in writing within 15 days and offer an alternative connection point. The new measures are designed to speed up the rollout of rooftop solar and boost North Macedonia’s renewable energy development.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia June generation drops 13.2% as solar output declines

North Macedonia’s gross electricity production decreased 13.2% year on year to 408,045 MWh in June. The figures were released against a backdrop of drought and high temperatures affecting system operation. Electricity from thermal power plants totaled 131,405 MWh, down...

Serbia–North Macedonia gas interconnector enters implementation phase, linking to Greek LNG

Serbia and North Macedonia have moved their planned gas interconnector into the implementation phase. The project is designed to strengthen a northbound supply route connecting the Serbian market with Greek LNG infrastructure and the Southern Gas Corridor. Implementation agreement...

North Macedonia to join Vertical Gas Corridor in September

North Macedonia plans to join the Vertical Gas Corridor in September. The move is aimed at shifting the country’s gas system from a relatively isolated national network to a wider north-south supply route across Southeast Europe. The corridor entry...
Supported byVirtu Energy