North Macedonia: Government to cancel tender for HPP Cebren

Macedonian government will cancel a tender for the construction of the 333 MW Cebren hydropower plant, valued at 1 billion euro, after the selected consortium, composed of Greek companies PPC and Archirodon, failed to fulfil the conditions required for signing a concession contract, environment minister Kaja Shukova announce.

The Greek companies encountered difficulties obtaining funding for the project due to specific conditions in the tender, leading the government to reject the extension of a banking guarantee, Shukova told a press conference streamed on the Facebook profile of Macedonian Information Agency.

The banking guarantee was a precondition for signing the concession contract for the project, the minister added.

The government decided to award the concession contract for the construction of Cebren HPP to the Greek consortium in September 2023.

The project is planned to be carried out as a public-private partnership with state-owned electricity company ESM.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Electricity tariff review in North Macedonia targets 2027 regulated charges

Regulated power prices for 2027 under Energy Regulatory Commission review North Macedonia has started reviewing regulated electricity prices for 2027, with the government facing pressure to limit higher energy costs for households and small businesses. The review comes as transmission...

North Macedonia’s electricity trading jumps 74% as September prices rise

Electricity traded on North Macedonia’s MEMO day-ahead exchange rose 74% year on year to 179.2 GWh in September, pointing to increased participation and growing use of the organised electricity market. Despite the strong annual increase, trading volumes fell 10.3% from...

Serbia plans North Macedonia gas interconnector construction start, aiming Q1 2028

Pipeline scope and early works near Vranjska Banja Serbia is targeting early 2028 completion for its gas interconnector with North Macedonia, with construction planned to start and reach completion in the first quarter of 2028. Initial works near Vranjska Banja...
Supported byVirtu Energy