Montenegro: TPP Pljevlja back online after maintenance

 

Montenegrin coal-fired thermal power plant Pljevlja has been successfully reconnected to the grid following the completion of regular annual maintenance, EPCG announced. The regular overhaul began on April 17. It included a standard overhaul of the machinery hall, boiler plant, coal dust preparation system, and auxiliary facilities. This year, there was an increased scope of work on the medium-voltage equipment, particularly the control and monitoring systems of the power plant.

EPCG also said that the environmental reconstruction of TPP Pljevlja is in progress. 71% of the construction work has been completed, and it is expected that the major construction work will be finished by mid-August.

The most significant facility being constructed as part of the project is the desulfurization plant, which will significantly improve the environmental conditions in Pljevlja, along with the denitrification facility. Additionally, a wastewater treatment plant, noise suppressors, and the construction of a permanent heating plant, which will serve as a backup source for district heating in the city, are also included in the project.

Upon completion of the environmental reconstruction project in 2024/2025, TPP Pljevlja will become one of the most modern facilities of its kind, fully compliant with EU directives regarding environmental standards, according to EPCG.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy