Montenegro: Solar Global advances 200 MW Cetinje solar project with minimal environmental impact

After receiving urban-technical approval in September of last year, the local company Solar Global has advanced its plans by submitting a request to the Environmental Protection Agency to assess whether a full environmental impact study is necessary for its proposed solar power plant in Cetinje.

A solar irradiation assessment conducted by Sedam-ING concluded that the location is highly suitable for a 200 MW solar facility. The plant is expected to generate approximately 438 GWh of electricity annually.

The proposed installation will cover an area of about 119 hectares and will include 256,000 solar panels, supported by 80 inverters and 40 transformers to ensure efficient energy conversion and seamless integration into the power grid.

According to the project overview and environmental impact analysis, experts have determined that the construction and operation of the facility are unlikely to cause significant environmental harm. Additionally, there are no nearby developments that might lead to cumulative effects on the surrounding ecosystems.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG submits environmental assessment for 37.6 MW Kapino Polje B2 solar plant

Montenegro’s state-owned power utility EPCG has submitted an environmental-impact assessment for its planned 37.6 MW Kapino Polje B2 solar power plant near Nikšić, advancing the project through the permitting process. The filing relates to a facility identified as Kapino...

MMK Vilusi requests environmental screening for 35 MW solar plant in Nikšić

MMK Vilusi has applied for environmental screening for a 35 MW solar power project in western Montenegro, with the development planned for the Nikšić municipality. The request is described as an early regulatory step in the project’s permitting process....

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...
Supported byVirtu Energy