Supported byClarion Energy
HomeSEE Energy NewsMontenegro: Extension of...

Montenegro: Extension of TPP Pljevlja expected

Although the previously undertaken obligations to complete the modernization of the TPP in 2020 have not been completed, it is unlikely that Montenegro will be asked to close it, because other deadline extensions were already granted to other countries in the region.

Negotiations with the Energy Community (EnC) on the continuation of the operation of coal-fired thermal power plant Pljevlja, which expended the previously approved 20,000 operational hours with environmentally unacceptable technology, will continue this week, and the result could be known in four to five months.

TPP Pljevlja now accounts for 40 % of Montenegro’s electricity production, and in dry periods of the year this number is over 50 %. Its shutdown would mean that Montenegro must import a huge amount of electricity, which would affect the growth of electricity prices for all categories of consumers by 20 to 25 % and the loss of 1,200 jobs in the thermal power plant and adjacent coalmine.

The Ministry of Capital Investments, which took over the energy department from the former Ministry of Economy, and state-owned power utility EPCG, which operates the plant, believe that the chances for such a scenario are minimal. They expect that the negotiations will be successfully completed, that they will get additional operational hours with the current technology, but also that there will no longer be an obstacle for the environmentally-oriented reconstruction of the plant to be completed by the end of 2022. In June 2020, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The deadline for the completion of works is 39 months for the date of signing the contract. The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. Project implementation is scheduled to take place in the period 2019-2021, after which the operation of TPP Pljevlja will be enabled to continue for at least 20 years. Reconstruction will assure compliance with the requirements and adherence to the strictest environmental protection parameters as envisaged under the latest EU Decision 2017/1442.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...
Supported byVirtu Energy