Supported byClarion Energy
HomeSEE Energy NewsMontenegro: Extension of...

Montenegro: Extension of TPP Pljevlja expected

Although the previously undertaken obligations to complete the modernization of the TPP in 2020 have not been completed, it is unlikely that Montenegro will be asked to close it, because other deadline extensions were already granted to other countries in the region.

Negotiations with the Energy Community (EnC) on the continuation of the operation of coal-fired thermal power plant Pljevlja, which expended the previously approved 20,000 operational hours with environmentally unacceptable technology, will continue this week, and the result could be known in four to five months.

TPP Pljevlja now accounts for 40 % of Montenegro’s electricity production, and in dry periods of the year this number is over 50 %. Its shutdown would mean that Montenegro must import a huge amount of electricity, which would affect the growth of electricity prices for all categories of consumers by 20 to 25 % and the loss of 1,200 jobs in the thermal power plant and adjacent coalmine.

The Ministry of Capital Investments, which took over the energy department from the former Ministry of Economy, and state-owned power utility EPCG, which operates the plant, believe that the chances for such a scenario are minimal. They expect that the negotiations will be successfully completed, that they will get additional operational hours with the current technology, but also that there will no longer be an obstacle for the environmentally-oriented reconstruction of the plant to be completed by the end of 2022. In June 2020, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The deadline for the completion of works is 39 months for the date of signing the contract. The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. Project implementation is scheduled to take place in the period 2019-2021, after which the operation of TPP Pljevlja will be enabled to continue for at least 20 years. Reconstruction will assure compliance with the requirements and adherence to the strictest environmental protection parameters as envisaged under the latest EU Decision 2017/1442.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

World Bank-backed €50 million programme targets district heating in Pljevlja

Pljevlja transition programme and heating measures Montenegro is preparing an approximately €50 million World Bank-backed investment programme for Pljevlja. The effort targets district heating, cleaner household energy and efficiency measures as the country begins building infrastructure for an eventual transition...

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...
Supported byVirtu Energy