Montenegro, EPCG hired contractors for the district heating project in Pljevlja

Montenegrin state-owned power utility EPCG has signed a 2.5 million euros worth contract for the construction of the district heating system in the city of Pljevlja in northern Montenegro with the consortium consisting of local company Roto-Term and Serbian company Synergy Tech.

According to the contract, the consortium should develop the main design of the heating system, as well as build the main line between the coal-fired thermal power plant Pljevlja and the city in the length of 2.3 kilometers. The contract covers the first phase of the Pljevlja district heating project.

In May, EPCG signed a contract with the Public Works Administration on the construction of district heating system in the city of Pljevlja worth 5 million euros, which will be developed in two phases.

In April, EPCG said that it has started the environmentally oriented reconstruction of the country’s sole coal-fired thermal power plant Pljevlja, with the aim of increasing the plant’s operational life. The project’s value is 70 million euros and it should be completed in two and a half years.

In June 2020, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. EPCG later decided to invest additional 15 million euros in the reconstruction.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...